Cash Paid for Building Church                    1885
-------------------------------------------------------------------

Sept.  5th   William (not sure of last name, ) Stauntan
             Architect.                                     25.00

        "    W. C. Warrel, lime                              3.30
        "    Mr. Walker (carpenter)                         10.00
       19th  Mr. Walker-Mr. Legrand & Mr. Stevens.          59.50
       25th  Laborers-                                       2.60
       27th  Carpenters                                     33.00

Oct.   10th  Adam Fox-Foundry Work                          63.00
       10th  Carpenters                                     56.25
       13th  Sundry Items for Church                         2.50
       17th  Carpenters & Freight upon train-               35.50
        9th  S. Spangler- Lumber                           335.56
       24th  Carpenters-                                    24.00
       24th  H. Blackburn (work)                             7.00
       31st  Carpenters-                                    26.25
Nov.    5th  Carpenters-                                    10.00

         10th  Carpenters-                                    10.00

Nov.    4th  Due Hyland & Hankinson-for freight bills,
             nails & labor.                                 62.00
        4th  Bill due S. Spangler-bill due for brick.        9.00

Mr. Legrand will complete the building, by contract, at $150

(So it seems that the basic Church building cost was $924.46 plus incidentals)